Mezzanine Stairs Appear

Wednesday, September 30, 2009

Comments Off on Mezzanine Stairs Appear

Mezzanine Stairs Appear

Yesterday Red and his crew installed the steel for the mezzanine stairs (and handrails). Matt Decell will follow up with the treads, which are being made from some of the old beams that were removed from the ceiling. The stairs have a big impact on the space…and bring to life the diagonal run that KHA […]

New Windows

Friday, September 25, 2009

Comments Off on New Windows

New Windows

Digging the new windows in the back alley. Actually, they’re the old windows. But new and improved. After some internal “discussion,” and a gentle suggestion from those at the BAR, we wound up refurbishing the existing windows (were full of wired glass, and treated with a few bullet holes). They look great with the new […]

Let there be even more light

Friday, September 18, 2009

Comments Off on Let there be even more light

Let there be even more light

They're continuing to set the glass wall today. Should be done soon.

Let there be light

Thursday, September 17, 2009

Comments Off on Let there be light

Let there be light

At long last, the glass wall is going up this week. It’s amazing to see how much light is shed into the work space with even just a few panels. You’ll also notice the wood flooring that was laid last week.

Labor Day Status

Monday, September 7, 2009

Comments Off on Labor Day Status

Labor Day Status

This weekend the painters have been working hard to prime all the walls and ceilings.